7. No work shall be carried out on site for the development hereby approved, until full
written details for a Code of Construction Practice has been submitted and approved in
writing by the Local Planning Authority. The Code of Construction Practice should detail
good practice measures for site working to mitigate potential impacts from construction
including protection of retained features and surface water bodies on or adjacent to the
site, control of run-off, application of design controls for construction equipment and
construction vehicles, vehicle routing, wheel washing facilities, sheeting of lorries during
transportation of construction materials, provision of water sprays during delivery and
dumping of sand and gravel, mixing and batching on wet rather than dry aggregate
materials, minimum drop heights to be used for continuous and batch drop activities and
waste disposal. The approved Code of Construction Practice shall be implemented
throughout the period of work on site. C04(M)
LATIMER, THAKEHAM, CLARION (GROUP) - LIST OF PERSONS INVOLVED IN THE DEVELOPMENT
Peter Rawlinson - Gleeson Strategic Land Ben Rainbow - Arboricultural & Biodiversity Officer Steve Tuhey - Managing Director, Thakeham Client Richard White, Director of Land and Planning at Latimer & Clarion Housing Group
LATIMER DEVELOPMENTS - Previously: William Sutton Developments Limited
Christopher John Hatfield Ruth Margaret Cooke David Simon Fordham Austen Barry Reid Rupert Owen Sebag-Montefiore Mark Christopher Rogers David Anthony Lewis Michelle Reynolds
Southern Water - Nick Claxton Team Manager – Flood Risk Management & Revai Kinsella, Principal Drainage Officer .
WD/2015/0090/ HERSTMONCEUX VILLAGE CONDITIONS A - Z INDEX
WD/2015/0090/MAO - GLEESON DEVELOPMENTS LTD
This application is not only contrary to Wealden's Local Plan, but is considered by many to be downright dangerous. The A271 is a narrow country road that is already overloaded - with many traffic jams in the village high street causing motorists serious delays on occasion. The increase in traffic from a dense residential development at this location is nothing short of madness.