9 NOISE & HOURS - WD/2015/0090/MAO
Please use our A-Z INDEX to navigate this site
|
WD/2015/0090/MAO - CONDITION 9 - SITE NOISE & WORKING HOURS
9. During construction, no audible works shall take place other than within the hours
Monday to Friday 08:00 to 18:00 hours, Saturday 08:00 to13:00 and not at all on
Sundays or Public/Bank Holidays. All works shall ensure compliance with guidance found
in British Standard ‘ BS5228-1:2009 - Code of practice for noise and vibration control on
construction and open sites-Part 1:Noise’.(M)
LATIMER, THAKEHAM, CLARION (GROUP) - LIST OF PERSONS INVOLVED IN THE DEVELOPMENT
Peter Rawlinson - Gleeson Strategic Land Ben Rainbow - Arboricultural & Biodiversity Officer Steve Tuhey - Managing Director, Thakeham Client Richard White, Director of Land and Planning at Latimer & Clarion Housing Group
LATIMER DEVELOPMENTS - Previously: William Sutton Developments Limited
Christopher John Hatfield Ruth Margaret Cooke David Simon Fordham Austen Barry Reid Rupert Owen Sebag-Montefiore Mark Christopher Rogers David Anthony Lewis Michelle Reynolds
Southern Water - Nick Claxton Team Manager – Flood Risk Management & Revai Kinsella, Principal Drainage Officer .
WD/2015/0090/ HERSTMONCEUX VILLAGE CONDITIONS A - Z INDEX
WD/2015/0090/MAO - GLEESON DEVELOPMENTS LTD
This application is not only contrary to Wealden's Local Plan, but is considered by many to be downright dangerous. The A271 is a narrow country road that is already overloaded - with many traffic jams in the village high street causing motorists serious delays on occasion. The increase in traffic from a dense residential development at this location is nothing short of madness.
LINKS & REFERENCE
https://thakeham-client.com/ http://www.clarionhg.com/news-research/2018/march/latimer-to-deliver-70-new-homes-in-herstmonceux/ https://www.gov.uk/ http://www.english-heritage.org.uk/
|